The San Francisco Bay Bridge was closed down for 5 days over the Labor Day Weekend to slide out an old section of bridge and slide in a new section of roadway creating a detour so the new Bay Bridge Replacement could continue |


|
THe Bridge on the left will be remove to build the new Bay Bridge,the bridge on the right is a temporary structure |


|
Where the new and the old come together |


|
Thi is part of the jacking system that will be used to moved the bridges |


|
The new bridge on the right was built next to the old bridge, the bridge is 300 feet long and wieghs approx 3300 tons |



|
It took approx 2 hours to slide th old bridge section out(the section on the right side)and begin prepping for the new xection to be moved into place
The old bridge is moved onto falsework |





|
The old section moved onto temporary falsework, then the falework will be removed and the bridge section will then be lowered with cables and dismanteld |


|
The old deck section has been moved out of the way for the new deck section |


|
The old deck has been moved leaving 300 foot gap |




|
The New Deck section was built 150 feet above the ground next to the Old Bridge section |


|
The New Bridge section is being slid into the gapping hole ,the workers use Dawn dishwashing soap for lubication on the tracks |


|
This is where we had our meals provide by the contractor
The old bridge has been moved out and new bridge is almost in place |


|
The old bridge is out of the way and the new bridge is almost in place |


|
Old Deck Section |



|
New Deck Section being moved in |









Please wait while we load